What is the Wekiva Parkway Expansion?
The Wekiva Parkway, also known as State Road 429, is a stretch of highway that will connect with SR417 and form a beltway around Central Florida. This new tollway is meant as an alternative for I-4 and to help relieve traffic and congestion on US 441 and SR 46. The Wekiva Parkway will be the first expressway in Central Florida to feature All Electronic Tolling. This means there will be no toll plazas so motorists will not need cash. No more slowing down or stopping to pay tolls.
This project is being completed in sections. There are 4 sections which will run through Seminole county; Sections 6, 7A, 7B, and 8.
Click on Map to see whole project
Photo and Map credit: www.wekivaparkway.com
Expected Start and End Times
Clink on each Section for maps, pictures and details of each section
Section 6 - Start: 4th Quarter 2017, Completion: 1st Quarter 2021
Section 7A - Start: 2nd Quarter of 2018, Completion: 4th Quarter 2020
Section 7B - Start: 3rd Quarter of 2019, Completion: 1st Quarter 2021
Section 8 - Start: 4th Quarter of 2018, Completion: 4th Quarter 2021
Neighborhoods which will be affected
Click on a neighborhood to find out time lines for the start and end of the road